Schuyler Ave, Kearny

Objectives

The Passaic Valley Sewerage Commission (PVSC) has rehabilitated the Kearny-Harrison-Newark (KHN) Branch Interceptor Sewer on Schuyler Avenue between Tappan Street and King Street within the Town of Kearny.

Restoration and cleanup are expected to continue through June. Most of the duration of this work will have minimal traffic impacts, but there will be intermittent parking and traffic disruptions on Schuyler Avenue, including periods of lane closures and detours.

The Passaic Valley Sewerage Commission recognizes that the nature and duration of this project will have an impact on the local community. However, the infrastructure work, which is being performed on an emergency basis due to the failed condition of the interceptor, is critical to ensuring the health and safety of area residents and businesses.

Schedule updates will be posted on this site as they are available.

Locations

Schuyler Ave, from King Street to Dukes Street, in Kearny

SCHEDULE

Construction from March 2017 through May 2017. Restoration and cleanup work to continue through June.